Burchills Engineering Solutions were engaged by Avon Capital Estate to conduct civil engineering services design and contract administration of the civil construction of a five stage rural residential development located in Ipswich that consists of 96 acreage lots.

Burchills was responsible for:

  • Preliminary design & estimates;
  • Detailed civil design for Operational Works applications;
  • Tendering for the construction;
  • Construction supervision & coordination; and
  • Contract administration.

The construction of the first stage of the development was commenced in late 2017 and the final stage of the development was completed in late 2020. The scope of a combined $6 million project that were delivered include:

  • 30,000 cu.m of bulk earthworks;
  • 25,000 sq.m of roadworks;
  • 3,200 l.m of Stormwater drainage; and
  • 3,300 l.m of portable watermain.

The project also included external road widening on Arthur Summerville Road.