Burchills were engaged by QM Properties Pty Ltd to provide a preliminary engineering and to be considered as part of their acquisition of land, to create and expand the proposed development in Jimboomba. This analysis outlined the surrounding sites suitable for the expansion of the proposed development, relating to civil engineering design parameters and site constraints. The acquisition of number of land parcels resulted to 372 residential allotments

Burchills were engaged to complete the following:

  • Feasibility Analysis;
  • Conceptual Stormwater management Plan including
  • Trunk Detention Basins ;
  • Preliminary designs & estimates;
  • Reginal Water and Sewer network Analysis;
  • Detailed Civil Design for OPW applications; and
  • Contract Administration & Supervision.

Stages 1,2,3 & 4 have been designed and OPW approval obtained.

Stages 1 & 4 have been completed early 2020. Stages 2 & 3 are currently under construction. Stages 5-12 pending DA approval and expected detailed design commencing September 2020.